Delivery of large windows and glass elements: how your glass front reaches site safely

6 minutes read

The delivery of large windows and lift-and-slide doors needs preparation: a passable access route for the lorry, space and equipment for unloading, a dry storage area where the elements can stand upright, and enough helpers or lifting gear for the route to the installation point. If you clarify these points before the delivery date, you avoid glass breakage, waiting time and extra costs.

Why large glass elements need special logistics

Glass is heavy and fragile. With a density of around 2.5 g/cm³, every millimetre of glass thickness weighs about 2.5 kg per square metre. A typical triple glazing with three 4 mm panes comes to around 30 kg/m². For a sliding sash with 6 m² of glass, that is about 180 kg for the glass alone; larger formats with thicker panes are well above that. Modern lift-and-slide hardware is designed for sashes up to 400 kg, and these are exactly the weights that have to be moved on delivery.

Then there is the size. Aluminium lift-and-slide systems allow sashes up to 3.5 m high; whole elements can be several metres wide. Such dimensions do not fit through every yard entrance, stairwell or front door.

Before the delivery date: what to clarify

Access

  • Road and driveway: can a lorry with a rack body drive right up to the house? Are there weight restrictions, tight bends, low clearances or tree canopies?
  • Parking restrictions: on narrow streets, a parking suspension for the delivery day may be necessary. In the UK this is arranged through the local council; elsewhere, through the local traffic authority. Apply in good time.
  • Ground: is the unloading area paved? Unmade ground on site may be impassable after rain.

Unloading

  • Tail-lift or vehicle crane: what equipment does the haulier bring? Is it sufficient for the weight of the heaviest unit?
  • Forklift or crane on site: on new builds a tower crane is often available; agree the date with the site manager.
  • Personnel: who helps unload? Kerbside delivery usually means the goods are handed over at the vehicle; carrying them into the building is not automatically included.

Route to the installation point

Measure doors, corridors, stairs and turns on the route from the unloading point to the installation point. Large elements often cannot be carried through the house but have to be brought directly to the opening from outside. For installation on an upper floor, a crane may be needed.

Storage on site

The guideline of the German Federal Association of Flat Glass on handling multi-pane insulating glass sets out clear rules that apply by analogy to finished window and door elements:

Rule Why
Stand only upright on suitable racks flat storage stresses glass and edge seal
Interleaving between stacked units prevents scratches and pressure marks
Cover fully outdoors protection from prolonged moisture and sun
Limit deflection at the edge (max. 1/200 of the edge length, at most 15 mm) protects the edge seal
Check for damage before installation spot damage in good time

In practical terms: stand the elements against a load-bearing wall or on the delivery rack, secure them against falling over and cover them. Do not store glass in full sun under dark sheeting; the heating can cause thermal stresses. Keep away from grinding, welding and angle-grinder work: sparks and grinding dust burn into glass surfaces.

Goods receipt: check before you sign

You or your site manager should be present at delivery. Check:

  1. Completeness: do quantity and positions match the delivery note?
  2. Dimensions and specification: spot-check dimensions, colour, opening direction and scheme.
  3. Visible damage: broken glass, scratches, dents in the frame, damaged packaging.
  4. Accessories: handles, cover caps, fitting materials, connection profiles.

Note any damage directly on the delivery note before you sign and document it with photos. Report hidden defects that only become visible on unpacking immediately. How to make a complaint properly is explained in the article complaints about windows.

Carrying and fitting

Large sashes and fixed panels are moved at the installation point using suitable aids:

  • Glass trolleys or roller trolleys for level routes
  • Vacuum lifters with suction plates for lifting and fitting
  • Mini crane or glass manipulator for very heavy elements
  • Enough personnel: it is better to plan for one person more.

Always carry elements on edge and do not grip insulating glass by a single pane but by the frame or with suction cups on both sides. What happens after delivery is described in the article installing a lift-and-slide door.

Special points for deliveries abroad and for trades

For deliveries to other EU countries, longer transport routes and sometimes different vehicle types come into play. Clarify whether the haulier can drive to the site or whether the goods are handed over at a transfer point. For trade firms that have several projects delivered, it is worth bundling delivery dates and agreeing binding delivery time windows. Also check whether empties such as transport racks are taken back and who collects them.

With consolidated deliveries of several items, the elements should be clearly labelled, for example with the position number and room name from the order. That way the installation team finds the right element for each opening without opening all the packaging.

Weather and season

Strong wind is dangerous when unloading and carrying large areas of glass: a pane acts like a sail. Postpone unloading in a storm. In winter, elements should not stand for long in the cold before installation if sealants that need a minimum temperature are to be used afterwards. In rain: cover, but provide ventilation so that no condensation collects under the sheet.

Coordinating delivery and installation date

Ideally, delivery is timed so that the elements stand on site only briefly. Agree the delivery date with the installation team. On new builds, the opening should be prepared, the screed laid or the height fixed and access clear. In a renovation, it must be clear when the old door will be removed, so that the house does not stand open overnight. How to plan realistic time windows is covered in the article lead times for windows and doors.

Tip: appoint one responsible person for each delivery who can be reached by phone and is allowed to make decisions, for example where to unload if the planned spot is blocked.

Checklist for delivery day

  • Access and unloading area checked, parking suspension applied for if necessary
  • Unloading equipment agreed with the haulier
  • Helpers or lifting gear organised for the route to the installation point
  • Dry, level storage area with cover prepared
  • Delivery note and order to hand
  • Goods receipt documented with photos
  • Installation date confirmed

AluKun delivers windows, doors and lift-and-slide elements to Germany and the EU. You will see the delivery terms for your project in the quotation. Start with your lift-and-slide door in the configurator or ask about delivery via the contact form.

Frequently asked questions

How are large windows and sliding doors delivered?

Large elements are transported upright on racks and, depending on weight, unloaded with a tail-lift, vehicle crane or forklift. Until installation they must be stored upright, dry and protected.

What do I need to check on receipt of goods?

Check the quantity, dimensions and positions against the delivery note, and look for visible damage to glass, frame and packaging. Note any damage on the delivery note and document it with photos before you sign.

May insulating glass be laid flat?

No. According to the guideline of the German Federal Association of Flat Glass, multi-pane insulating glass may only be stood in a vertical position on suitable racks.

How many people does it take to carry a lift-and-slide door?

That depends on the weight. A sliding sash with several square metres of triple glazing quickly weighs over 150 kg. Loads like that need several people and aids such as glass trolleys or vacuum lifters.

Sources

  1. BF-Merkblatt 002 – Richtlinie zum Umgang mit Mehrscheiben-Isolierglas(opens in a new tab)
  2. Floatglas – Wikipedia (Dichte, Bandmaß)(opens in a new tab)
  3. Isolierglas – Wikipedia (Gewicht Dreifachverglasung)(opens in a new tab)
  4. Schüco Schiebetüren – maximale Flügel- und Elementmaße(opens in a new tab)
  5. SIEGENIA PORTAL HS 400 kg – Hebe-Schiebe-Beschlag(opens in a new tab)

Ready for your project?

Configure your products to measure and see the price straight away – or send us your questions.

Cover image: Lift-and-Slide Door Installation: Process and Rules
Lift-and-slide doors

Lift-and-Slide Door Installation: Process and Rules

Installing a lift-and-slide door: preparation, threshold, fixing, sealing and adjustment step by step, so you can recognise professional workmanship.

6 minutes read

Cover image: Toughened and Laminated Glass: When It Is Required
Lift-and-slide doors

Toughened and Laminated Glass: When It Is Required

Toughened or laminated glass in windows? Differences, breakage behaviour, standards and when safety glass is required under DIN 18008, explained with examples.

7 minutes read

We use strictly necessary cookies so the shop, configurator and basket work. With your consent we also use Google Analytics to measure how the site is used, and marketing signals for advertising. You can change your choice at any time in the footer. Read our privacy policy