Skip to content

Business customers only (B2B) · All prices net plus VAT

AluKun
Costs & buying guides

Lead Times for Windows and Doors: How to Plan Delivery Dates Realistically

7 minutes read

The lead time for windows depends above all on material, colour and special specification. Published figures from online suppliers are a few weeks for white uPVC windows and markedly longer for aluminium, special colours and large lift and slide doors. If you want to plan realistically, allow not only for production time but also for survey, technical clarification, transport and the fitting date. The figures here come from German suppliers and are examples only; lead times elsewhere will differ.

This article shows which factors determine lead time, what orders of magnitude suppliers publish and how to align your building schedule with them.

Window Lead Times: What Suppliers Publish

There is no universal lead time. Two publicly available sets of figures do show the typical staggering, however:

Product Fensterversand Fensterblick
uPVC windows, white 2–5 weeks 2–8 weeks (uPVC)
uPVC, special colours 4–7 weeks –
Aluminium, standard colours 3–6 weeks 6–12 weeks (aluminium)
Timber – 10–16 weeks
Timber-aluminium – 12–16 weeks
Front door, uPVC, white 2–5 weeks –
Lift and slide door, uPVC, white 4–7 weeks –
Lift and slide door, uPVC, special colour 7–10 weeks –
Lift and slide door, aluminium 8–10 weeks –

These values apply to the suppliers concerned and their manufacturing partners. They do show the pattern that repeats across the industry: white is fastest, colour and aluminium take longer, timber longest, and large sliding elements lie above standard windows. Only your supplier's statement in the order confirmation is binding. Check whether it gives a calendar week, a period or merely a non-binding "approx." figure.

What Lengthens the Lead Time

Colour and Finish

Foiled uPVC profiles or powder-coated aluminium profiles in special colours are often coated to order. That takes time; with aluminium, coating is an additional production step. Why colours also cost a surcharge is explained in the article Colour surcharge on windows.

Glass

Standard triple glazing is usually quickly available. Acoustic glass, safety glass (laminated, P4A), patterned glass or solar-control coatings are sometimes ordered separately and lengthen the time.

Special Shapes and Oversize

Round arches, slopes, very large fixed glazing or heavy lift and slide elements need special production steps and often separate transport as well.

Factory Holidays and Season

Fensterversand points to plant closures around Easter, Whitsun, in summer and over Christmas. The season also plays a role: many self-builders want to finish before winter, and in spring numerous renovations start at the same time.

Material Shortages

Shortages of profiles, glass or hardware can lengthen lead times at short notice. Reputable suppliers tell you as soon as it affects your dates.

Transport

If the windows come by freight forwarder, Fensterversand allows two to three working days for delivery. For deliveries abroad or to islands it can take longer.

From Enquiry to Fitting: A Realistic Schedule

Production time alone is only part of it. Plan the whole chain:

  1. Planning and selection: decide profile, glass, colour and opening types.
  2. Apply for funding if you are using BAFA funding in Germany; the application must be made before the contract is signed.
  3. Survey: in existing buildings on the old window or the wall opening, in new builds on the finished shell.
  4. Order and technical clarification: answer queries on dimensions and specification.
  5. Order confirmation: from here the lead time normally runs.
  6. Production and transport.
  7. Fitting: agree the date with the fitting firm.

Between steps 1 and 5 there can also be several weeks, depending on how quickly you decide and on the funding procedure.

New Build: When to Order Windows

In a new build many trades depend on the windows: internal plaster, screed, façade and electrics. Fensterblick recommends planning windows and external doors as early as possible at the start of the shell. Two strategies are usual:

  • Survey on the shell: as soon as the walls are up, measure and order immediately. Advantage: exact dimensions. Disadvantage: the lead time falls within the construction period.
  • Order from the drawings: the windows are ordered earlier to design dimensions. Advantage: time gained. Disadvantage: deviations of a few centimetres in the masonry can cause problems.

You can read more on coordination with the building schedule in the article New build: planning and ordering windows early.

Renovation: Using the Time Window Wisely

In existing buildings the lead time is less critical because the old windows stay in until fitting. Plan for the following all the same:

  • Season: windows can be replaced all year round, but frost sets limits for sealants and plastering. Advice is given in the article Replacing windows in winter.
  • Combined measures: if façade or roller shutters are being done at the same time, all lead times should fit together.
  • Tenants and neighbours: in a block of flats, dates must be announced.

How to Shorten the Lead Time Yourself

Part of the waiting time is in your own hands:

  • Bundle decisions: fix colour, glass, handles and accessories before you order. Every later change resets the clock.
  • Choose standards where it does not matter: white uPVC profile in the cellar or utility room, colour where it is seen.
  • Answer queries quickly: technical clarifications on dimensions or opening directions delay the order confirmation if they are left lying.
  • Supply complete documents: a window list with room name, dimensions, opening type and hand avoids misunderstandings.
  • Align lead times of different products: if you order windows, front door and lift and slide door together, you often get a combined delivery, but it follows the slowest product. A part delivery can make sense.

What to Do If the Date Slips

Delays happen, for example through glass shortages or short-notice plant faults. Stay in close contact with your supplier then and ask for a binding new date. Inform the fitting firm and subsequent trades at once. In a new build, temporary sealing of the openings with sheeting helps so that screed or internal plaster is not left unprotected. How to proceed with contractually promised dates is something you should have checked legally if in doubt.

Accepting Delivery: What to Look For

  • Have the date confirmed and clarify access; large lorries need room.
  • Organise helpers: often delivery is only to the kerb, and unloading is up to you.
  • Check at once: check the number of items and visible damage and note it on the delivery note. In Germany, under § 438 HGB, where externally visible damage is not reported at the latest on delivery, the goods are presumed to have arrived undamaged; for damage that is not apparent a period of seven days applies. If you are elsewhere, check the local rules on reporting transport damage.
  • Store correctly: upright, dry, protected from sun and damage.

What to do about defects is explained in the article Complaints about windows.

Checklist for Realistic Dates

  • Get the lead time in writing with a reference point (from order confirmation)
  • Take factory holidays and public holidays into account in the schedule
  • Allow for special colours and special glass as a time factor
  • Reserve the fitting firm early
  • Inform trades that depend on the windows
  • Organise delivery, unloading and storage
  • Allow a buffer of two to three weeks between expected delivery and following trades

In the configurator you see all the specification options for your windows and can decide early, which saves time in technical clarification. For questions about dates on large projects you can reach us via the contact page.

Frequently asked questions

How long is the lead time for uPVC windows?

Published supplier figures for white uPVC windows are mostly a few weeks, for example two to five or two to eight weeks. Special colours, special glass and factory holidays lengthen this.

When does the lead time start?

As a rule from the order confirmation, after all technical details have been finally clarified and, if agreed, after payment is received. Ask your supplier what their figure refers to.

When should I order windows for a new build?

Plan windows and external doors as early as possible in the shell phase. Many self-builders take the measurements on the finished masonry and order straight away so that the windows can be fitted in good time before the internal plaster.

What lengthens the lead time of windows?

Typical causes are special colours and foils, special shapes, special glass such as acoustic or safety glass, large lift and slide doors, factory holidays and shortages of profiles or glass.

Sources

  1. Fensterversand: Lieferzeit für Fenster und Türen(opens in a new tab)
  2. Fensterblick: Hausbau – Wann die Fenster bestellen?(opens in a new tab)
  3. § 438 HGB – Schadensanzeige(opens in a new tab)
  4. Sofort-Förderung: Förderung für neue Fenster 2026 (Antrag vor Vertrag)(opens in a new tab)

Ready for your project?

Configure your products to measure and see the price straight away – or send us your questions.

Cover image: Anthracite Windows: Why Colour Costs More
Costs & buying guides

Anthracite Windows: Why Colour Costs More

Why do anthracite windows cost more? Foil finishing, reinforcement and extra production work explained, with current surcharge ranges and colour tips.

6 minutes read

Cover image: Front Door Cost: From Entry-Level to Designer Doors
Costs & buying guides

Front Door Cost: From Entry-Level to Designer Doors

What does a new front door cost? Market prices for uPVC, aluminium and timber, fitting, sidelights, security and funding, with tips for planning your budget.

7 minutes read

We use strictly necessary cookies so the shop, configurator and basket work. With your consent we also use Google Analytics to measure how the site is used, and marketing signals for advertising. You can change your choice at any time in the footer. Read our privacy policy