Planning Windows for a New Build: Timing, Survey and Decisions Before You Order
7 minutes read
Anyone planning windows for a new build should do so considerably earlier than many self-builders think. The windows determine when the house is closed in and when internal plaster, screed and building services can proceed. It is advisable to fix windows and external doors at the very start of the shell, take the measurements on the finished masonry and then order immediately.
This article shows which decisions you should make before the shell goes up, how survey and lead time fit into the building schedule and which mistakes you can avoid.
Planning Windows for a New Build: Why Timing Matters So Much
In the building schedule, many trades depend on the windows:
- Internal plaster needs windows already fitted so that the reveals are plastered cleanly.
- Screed is usually laid only when the house is closed in, partly because of drying.
- Electrics need clarity on roller shutter motors, window handles with contacts or smart-home connection.
- Façade and thermal insulation are connected to the window frames.
The Fensterblick guide points out that lead times can exceed the duration of the shell. Anyone who orders too late risks a standstill on site. What lead times suppliers publish is shown in the article Lead times for windows and doors.
Decisions Before the Shell
Some decisions have to be made before bricklaying because they affect the openings in the shell:
| Decision | Why it must be made early |
|---|---|
| Window sizes and sill heights | determine the wall openings |
| Roller shutter or external venetian blind, type | top-mounted, surface-mounted or built-in affects lintel height and opening |
| Floor-to-ceiling elements and thresholds | a flush threshold needs coordination with screed and waterproofing |
| Lift and slide doors | large openings, lintel and load transfer, transport route |
| Fitting position in the wall | important for thermal bridges and insulation |
| Opening directions | affect furnishing, radiators and sockets |
Other decisions can wait until the order, such as colour, handles, glass options and security specification. Do not leave these too late either, though: special colours and special glass lengthen the lead time.
Energy Requirements in a New Build
Unlike replacement in existing buildings, the German Buildings Energy Act (GEG) sets no fixed single value for windows in a new build. The building is assessed as a whole. What Uw value your windows must achieve follows from the energy demand calculation by your designer or energy consultant, often together with the requirements of a targeted efficiency house (Effizienzhaus) standard. Clarify this value before you choose profiles and glass. If you are building outside Germany, check the energy requirements in your national building regulations. Basics are explained in the article Uw, Ug, Uf: the U values of a window.
Survey: To the Drawings or on the Shell?
Fensterblick describes two routes:
Survey on the finished shell: as soon as the walls are up, the openings are measured and the windows ordered at once. Advantage: exact dimensions. Disadvantage: the lead time falls within the construction period, and the house stays open longer.
Order from the drawings: the windows are ordered early to design dimensions and stored until fitting. Advantage: time gained. Disadvantage: deviations of a few centimetres in the masonry can cause problems.
A middle way is to fix profile, glass and specification early, obtain a quote and trigger the order with the dimensions measured on the shell as soon as the openings are up. That way you shorten the time between survey and order confirmation.
Tips on measuring are in the article Measuring windows correctly.
Fitting Time and Building Schedule
According to Fensterblick, the ideal fitting period is after completion of roof and external walls and before internal and external plastering. Temperatures above freezing are favourable for fitting; with frost, special materials are needed. A typical sequence:
- Shell and roof complete
- Survey of the openings
- Delivery and fitting of windows and external doors
- Sealing of the connections inside and outside
- First-fix building services
- Internal plaster, then screed
- Façade or external render
Protect fitted windows during further building work with sheeting and edge protection. Plaster, mortar and screed cement can damage surfaces and seals. Also make sure there is enough ventilation while plaster and screed dry: with the new, airtight windows, construction moisture can otherwise condense on cold surfaces. Protective films on profiles should not stay in the sun too long, because they then become hard to remove.
Fitting Position in the Wall: Clarify Early, Save Later
With solid masonry the window usually sits centrally or slightly set back towards the inside of the wall. With walls with external wall insulation or a rainscreen façade, the window is often fitted further out or entirely within the insulation layer, on brackets or fitting frames. The fitting position affects:
- Thermal bridges: the better the window sits in the insulation layer, the lower the heat loss at the connection.
- Reveal depth inside: windows set further out give deep inside window boards, lovely as a seat but with less incoming light.
- Roller shutters and external venetian blinds: guide rails and boxes must suit the fitting position.
- Fixing: within the insulation layer the window needs special fixing systems.
Architect, window supplier and fitting firm should settle these details together before the shell goes up.
Plan Security from the Start
In a new build burglar protection can be integrated more cheaply than retrofitted later. It makes sense to provide burglar-resistant versions with tested hardware, lockable handles and safety glass for easily reached windows and doors: ground floor, lower-ground floor, balconies above garages. The resistance class applies only to the complete element including proper fitting. With large areas of glass on the ground floor it is also worth planning safety glass for personal protection.
Allow for Costs in a New Build Correctly
In a new build, removal and disposal are not needed, but other items are added:
- Connection tapes and foils for the airtight tie-in
- Fitting frames or brackets when fitting within the insulation layer
- Roller shutters or external venetian blinds including motor and electrical connection
- Window boards inside and outside
- Protective measures during the construction phase
How window prices are made up is explained in the article What do new windows cost?.
Typical Mistakes in a New Build
- Ordered too late: the house stays open, following trades stand idle.
- Roller shutter decision postponed: the lintel height no longer fits later.
- Thresholds not coordinated with the screed build-up: the patio door sits too high or too low.
- Opening directions not checked against furnishing: sashes strike against cupboards or radiators.
- Uw requirement not clarified: windows do not meet the value from the energy demand calculation.
- Transport route forgotten: large lift and slide elements no longer fit through the stairwell or over the scaffolding.
Checklist for Self-Builders
- Window list with sizes, opening types and sill heights before the shell
- Roller shutter or external venetian blind concept fixed
- Uw requirement from the energy design known
- Thresholds and floor build-up agreed with the designer
- Survey appointment on the shell planned
- Lead time confirmed and fitting date reserved
- Protection of fitted windows during the construction phase organised
- Ventilation concept for the drying phase discussed
In the configurator you put together made-to-measure windows, balcony doors and lift and slide doors and see prices and technical values already at the planning stage. For developers and trade businesses with several projects, it is worth asking about a company account through the contact page.
Frequently asked questions
When should I order windows for a new build?
Plan windows and external doors as early as the start of the shell. Often the measurements are taken on the finished masonry and the order placed at once, so that the windows can be fitted in good time before internal plaster and screed.
Can I order windows to the drawings before the walls are up?
That is possible and saves time, but carries a risk: deviations of a few centimetres in the masonry can mean that windows do not fit. Many self-builders therefore wait for the survey on the shell.
What minimum requirements apply to windows in a new build?
In Germany, a new build has no fixed single value for windows as with replacement in existing buildings; the Buildings Energy Act (GEG) assesses the building as a whole. The Uw value needed follows from your designer's energy demand calculation. Elsewhere, check your national building regulations.
When are windows fitted in a new build?
Usually after completion of the shell and roof and before internal plaster and screed. That way the house is closed in early, and the connections can be tied cleanly into plaster and insulation.