Acceptance and Handover: How to Inspect Your New Windows After Installation

7 minutes read

At the acceptance of new windows, you check together with the fitter whether all elements are correctly installed, work smoothly and have no visible damage. Anything that stands out belongs in the handover report. Acceptance is legally significant: it starts the limitation period for defect claims, and known defects must be expressly reserved by you. Take your time over it, ideally before the connection joints are plastered or lined.

The legal points below refer to German law (BGB). If you are outside Germany, the rules on acceptance, defects and limitation periods will differ, so please check them locally; the practical inspection checklist applies anywhere.

Why acceptance matters

Fitting windows is usually a contract for work. The German Civil Code (BGB) regulates acceptance in § 640:

  • Duty to accept: The customer must accept work that has been produced in line with the contract. Acceptance cannot be refused because of insignificant defects.
  • Deemed acceptance: If the contractor sets a reasonable deadline after completion and the customer does not refuse acceptance giving at least one defect, the work is deemed accepted. For consumers, this consequence arises only if the contractor has pointed it out in text form.
  • Reservation: Anyone who accepts defective work although they know of the defect keeps certain rights only if they reserve them at acceptance.

Under § 634a BGB, the limitation period for defect claims starts with acceptance. For work on a building, it is five years; for other work, generally two years. Which period applies to your contract depends on the individual case; this article does not replace legal advice. More on time limits in the article Warranty and guarantee.

Inspecting the windows: the on-site checklist

Frame, glass and surfaces

  • Frame and sash without scratches, dents or damage to the foil or coating.
  • Glass without scratches, cracks or misting in the cavity between the panes. Look at the pane in normal daylight from the usual distance, not with a torch in raking light.
  • Protective films fully removed, no adhesive residue.
  • Colours, finishes and glass types match the order, including safety or obscure glass.

Function and adjustment

  • Every sash opens, tilts and closes smoothly without rubbing.
  • The handle turns without excessive force; lockable handles work with all keys.
  • Sashes sit evenly in the frame, and the seals make contact all round. Paper test at several points; more in the article Replacing window seals.
  • Tilt position, mis-operation lock and ventilation gap function.
  • With lift-slide doors: lifting, sliding and lowering without jerking, threshold undamaged.

Installation and connection

  • Window installed plumb and level.
  • Connection joint fully taped airtight on the inside, no open corners or cracks. Check this before plastering; afterwards it can no longer be seen.
  • Driving-rain-tight connection present on the outside.
  • Fixings visibly present and not just in the foam.
  • Drainage openings in the frame clear.

The three-layer principle and how to check it is described in the article Sealed inside, open outside; the installation basics in the article RAL installation.

Window cill and roller shutter

  • External cill with fall outwards, sufficient projection and a drip edge.
  • Water test: pour water from a watering can onto the cill; it must drain away promptly, and the side connections stay dry.
  • Roller shutters run fully up and down, end positions are right, the bottom rail sits down. See Window cill and roller shutter.
  • Insect screen fits and can be operated.

The right time for acceptance

Ideally, acceptance takes place in two steps: a visual check of the connections straight after installation, while joints and tapes are still openly visible, and the formal acceptance after all work is finished, including window cills, roller shutters and making-good plaster. The specialist article on the three connection layers stresses that the time before plastering over is the only chance for a visual check of the sealing. If installation takes place in winter and external plastering is postponed, record the outstanding work in the report; more in the article Replacing windows in winter.

Allow enough time for acceptance: for a detached house with many windows, a careful inspection is not done in ten minutes. Take the report template, a camera or smartphone, a folding rule, a spirit level and a watering can.

The most common defects at acceptance

  • Sashes that rub or sag because of missing adjustment or wrongly placed glazing packers.
  • Damaged foil or powder-coated surfaces from transport or installation.
  • Missing or damaged internal sealing, especially in the lower corners.
  • External cill without sufficient fall or with open side connections.
  • Covered drainage openings in the frame.
  • Wrong type of glass, for example missing safety glass on floor-to-ceiling elements; see Toughened and laminated glass and when safety glass is required.

The handover report

A handover report records in writing what was checked and in what condition the work is handed over. It should contain:

Content Example
Date, place, those present client, fitter, site manager if applicable
Scope of work items according to the order, number of windows
Defects found exact description with room and position, photos
Reservations express reservation of rights for known defects
Deadlines agreed deadline for rectification
Outstanding work e.g. external making-good postponed because of frost
Signatures of both parties

Photograph each defect with an overview and a detail shot. Number the windows as in the order so that allocation and rectification are unambiguous.

Documents at handover

  • Invoice with a precise description of the windows, installation and ancillary services.
  • Declaration of performance with Uw-value and other performance figures; background in the article CE marking and declaration of performance.
  • Care and maintenance instructions for hardware, seals and surfaces.
  • Funding and tax documents: confirmations for the BAFA proof of use or the certificate under § 35c EStG (German schemes).
  • Security evidence: for burglar-resistant windows, evidence of the resistance class; the German police also recommend written confirmation from the specialist firm that installation was carried out properly.

Acceptance for windows without installation

If you buy windows without installation and fit them yourself or through a separate tradesperson, there is no acceptance in the sense of a contract for work with the supplier. Instead, you should check the goods immediately on delivery: quantity, dimensions, colours, glass and visible transport damage. Damage is noted on the delivery note and photographed before the windows are fitted. For the tradesperson's installation work, the rules on acceptance with that firm then apply. How to proceed when buying online is described in the article Buying windows online.

When defects appear

Minor defects such as a sash that rubs are usually adjusted straight away at acceptance. Larger defects are recorded in the report and put right within an agreed deadline. If defects appear only later, report them in writing with photos and set a reasonable deadline for rectification. How to proceed is explained in the article Complaints about windows.

Checklist

  1. Agree the acceptance date before the connections are plastered.
  2. Inspect each window individually: surface, glass, function, connection.
  3. Carry out the water test at window cills.
  4. Enter defects and reservations in the report, take photos.
  5. Take over and file the documents in full.
  6. Note and monitor rectification deadlines.

Careful planning starts when you order. In the window configurator you set all the details that you will find again at acceptance. If you have questions about your order, our team can help via the contact page.

Frequently asked questions

Why is the acceptance of the windows so important?

In Germany, acceptance starts the limitation period for defect claims under § 634a BGB. In addition, you lose certain rights for defects you know about at acceptance unless you expressly reserve them (§ 640 para. 3 BGB).

Can I refuse acceptance because of minor defects?

No. Under § 640 para. 1 BGB, acceptance cannot be refused because of insignificant defects. Such defects are recorded in the report and rectified.

What happens if I do not respond to the request for acceptance?

If the contractor sets a reasonable deadline and you do not refuse acceptance giving at least one defect, the work is deemed accepted. For consumers, this applies only if the contractor has pointed out this consequence in text form.

Which documents should I receive at handover?

The invoice stating the windows and services, the declaration of performance with the Uw-value, care and maintenance instructions and, where applicable, the certificate for funding or the tax bonus. For burglar-resistant windows, also evidence of the resistance class and of the installation.

Sources

  1. § 640 BGB – Abnahme(opens in a new tab)
  2. § 634a BGB – Verjährung der Mängelansprüche(opens in a new tab)
  3. dbfenster: Anschlussfuge am Fenster – die drei Ebenen(opens in a new tab)
  4. ift Rosenheim: Leitfaden zur Montage von Fenstern und Haustüren (7. Ausgabe)(opens in a new tab)
  5. Polizeiliche Kriminalprävention (K-Einbruch): Staatliche Förderung von Einbruchschutz(opens in a new tab)

Ready for your project?

Configure your products to measure and see the price straight away – or send us your questions.

Cover image: Fitting Windows in Timber-Frame and Prefab Houses
Shutters, security & installation

Fitting Windows in Timber-Frame and Prefab Houses

Fit windows in timber-frame and prefab houses: fixing, airtight connection to wood boards, driving-rain protection and replacing windows in a prefab house.

7 minutes read

Cover image: Replacing Windows in Winter: Does It Really Work?
Shutters, security & installation

Replacing Windows in Winter: Does It Really Work?

Replacing windows in winter: what to note in the cold, which fitting foams and tapes work, how the day runs and when it is better to wait.

6 minutes read

Cover image: Disposing of Old Windows: Removal and Recycling
Shutters, security & installation

Disposing of Old Windows: Removal and Recycling

Dispose of old windows: how removal works, where uPVC, timber and aluminium windows go, what German commercial waste rules require and where recycling works.

6 minutes read

We use strictly necessary cookies so the shop, configurator and basket work. With your consent we also use Google Analytics to measure how the site is used, and marketing signals for advertising. You can change your choice at any time in the footer. Read our privacy policy